A Gantt chart is a horizontal bar chart which can help you to track the projects in project management applications, with this type of chart, you can see the priorities of the tasks and the estimated completion of the project at a glance. But, create a Gantt chart may need a complex of steps in Excel, this article, I will introduce an easy tool-Kutools for ExcelGantt Chart, with this feature, you can quickly create a Gantt chart with only several clicks.

Create a Gantt chart based on start date and end date in Excel

Create a Gantt chart based on start date and duration in Excel


Create a Gantt chart based on start date and end date in Excel

If you have a task list with start date and end date as below screenshot shown, to create a Gantt chart, please do with the following steps:

shot gantt chart 01

1. Click Kutools > Charts > Point in TimeGantt Chart, see screenshot:

shot gantt chart 02

2. In the Gantt Chart dialog box, please do the following operations:

  • Select the range of cells that contains the task names from the Task Name box;
  • And then, choose the list of start date cells under the Start Date/Time box;
  • At last, select End Date/Time option, and select the end date cells from the data table.

shot gantt chart 03

3. Then, Click Ok button, a prompt box will pop out to remind you a hidden sheet will be created as well, see screenshot:

shot gantt chart 04

4. Click Yes button, a Gantt chart will be created immediately based on the start and end date, see screenshot:

shot gantt chart 05


Create a Gantt chart based on start date and duration in Excel

Sometimes, you have a range of data which include the start date and duration, you can also apply this feature.

shot gantt chart 06

1. Click Kutools > Charts > Point in TimeGantt Chart to apply this feature, and in the Gantt Chart dialog box, do the following operations:

  • Select the range of cells that contains the task names from the Task Name box;
  • And then, choose the list of start date cells under the Start Date/Time box;
  • At last, select Duration option, and select the duration cells from the data table.

shot gantt chart 07

2. Then, click Ok button, a prompt box will pop out to remind you a hidden sheet will be created as well, see screenshot:

shot gantt chart 04

3. Click Yes button, a Gantt chart will be created at once based on the start date and duration, see screenshot:

shot gantt chart 05

Note: In the first time you apply the Gantt Chart feature, you can click the Example button in Gantt Chart dialog box to open a new workbook with the sample data and sample Gantt Chart to know how it works.


Demo: Create a gantt chart with several click in Excel

 
Kutools for Excel: Over 300 handy tools at your fingertips! Enjoy permanently free AI features! Download Now!

Productivity Tools Recommended
The following tools can greatly save your time and money, which one is right for you?
Office Tab: Using handy tabs in your Office, as the way of Chrome, Firefox and New Internet Explorer.
Kutools for Excel: More than 300 Advanced Functions for Excel 2021, 2019, 2016, 2013, 2010, 2007 and Office 365.

Kutools for Excel

The functionality described above is just one of 300 powerful functions of Kutools for Excel.

Designed for Excel(Office) 2021, 2019, 2016, 2013, 2010, 2007 and Office 365. Free download and use for 30 days.

Screen shot of Kutools for Excel

btn read more      btn download     btn purchase

OSZAR »